One click, many sites
On a single router, a wrong command affects one router. In the Manager (formerly vManage), a wrong template value can reach every router attached to it. The Manager is also the only place most of the fabric is configured from, so this lesson is about the habits that keep that power safe, not about a particular screen.
One router against one template.
The stages of a change
Whatever the screen is called in your release, a safe change has the same stages. Plan decides what and why. Build creates or edits the template, configuration group or policy. Preview shows what will be sent. Push sends it to a small first group, then to the rest. Verify checks the result with the same commands used before the change. Record writes down what happened.
Plan, build, preview, push, verify, record.
- Planwhat, why, who
- Buildedit once
- Previewsee the diff
- Pushpilot first
- Verifysame checks
- Recordnote result
- Capture a baseline before the change: control connections, OMP summary and BFD summary on a pilot site, so that after the push there is something to compare.
- Choose a pilot, such as one branch like BR-02, before the group that has the hub.
- Decide in advance what result means success and what result means undo.
The preview stage is where most bad values can still be caught, but only if someone reads it. The table lists what to look for.
| Question | Why it matters |
|---|---|
| Is the changed line the one you meant? | A typo in a variable looks the same as a correct value until it is read |
| Does the device count match your plan? | A template attached to 40 sites reaches 40 sites, not the 5 you had in mind |
| Are there changed lines you did not touch? | Another engineer's edit to the same template goes out with yours |
| Does the change touch a transport interface or a route? | These are the changes that can cut a site off from the Manager |
Who may do what
Role-based access control (RBAC) in the Manager assigns users to groups, and each group has read or write rights per area, such as templates, policies, monitoring and administration. The aim is that the person who watches the dashboard cannot edit a template, and the person who edits a template cannot create new users. Group names and rights are release dependent.
A simple split of duties.
- Read-only operatorLooks at the dashboard, alarms and device statusNo edit rights
- Network engineerBuilds templates, groups and policiesMay preview and push in agreed windows
- AdministratorManages users, settings and controllersFew people, strong sign-in
| Control | Protects against | Where it shows |
|---|---|---|
| RBAC | The wrong person editing | User groups and rights (Administration area) |
| Configuration preview or diff | Pushing values you did not mean | Before the push, on the attach or deploy step |
| Pilot group | A problem reaching every site | Your own process, using device lists or tags |
| Audit log | Not knowing who changed what | Logs in the Monitor or Tools area |
| Backup before the change | No way back | Lesson on backups and lifecycle in this unit |
When a push goes wrong
Three outcomes cover most cases. The push is refused or stuck, because a device is unreachable or a value is invalid. The push succeeds but the device does not behave as intended, because the template was correct for a different site. Or the push succeeds and the device is cut off, for example by an interface or route change on the transport side. The third case is the dangerous one, because the Manager can no longer reach the device to fix it.
Refused, wrong result, or cut off.
- Not appliedunreachableinvalid value
- Wrong resultright config,wrong site
- Cut offtransport changed,control lost
- For a push that did not apply, read the task status in the Manager and fix the named value or device.
- For a wrong result, compare the pushed configuration with what the site needs, then correct the value for that site.
- For a device that was cut off, the fix is on the device or through another path. Some releases can roll back a push when the router loses contact; check yours, and do not rely on it without testing.
- Avoid pushing a change to transport interfaces to many sites at once. Push to one, confirm control connections stay up, then continue.
Worked example: the pilot that showed half the damage
A template change moves the MPLS gateway for 40 branches from 172.16.102.1 to 172.16.102.254, because the provider plans to move its gateways next week. Nobody has checked that the provider has done it yet. The plan names BR-02 as the pilot and records a baseline first. After the push, the pilot is compared with that baseline.
| Check | Baseline | After the push | Reading |
|---|---|---|---|
| Control connections up | 2 | 2 | Looks fine |
| OMP prefixes received | 7 | 7 | Looks fine |
| BFD sessions up | 4 | 2 | Stop |
| Transports with BFD up | mpls and biz-internet | biz-internet only | MPLS is lost |
BR-02#show sdwan bfd sessions 10.255.1.1 10 up biz-internet biz-internet 203.0.113.20 198.51.100.20 12346 ipsec 7 1000 0:00:13:58 10.255.1.2 20 up biz-internet biz-internet 203.0.113.20 198.51.100.40 12346 ipsec 7 1000 0:00:13:57
The pilot was lucky in one way: it had a second transport. A site that reaches the Manager only over MPLS would have been cut off by the same push, and the fix would then have needed a visit or another path. Suppose that 6 of the 40 branches are MPLS-only. A push to all 40 would isolate 6 sites, which is 15 percent of the estate, and every one of them would need hands on site. Pick pilots by site pattern, not by convenience.
| Site pattern | What a transport change can do | What the pilot shows |
|---|---|---|
| Two transports | Takes one transport down, the Manager still reaches the router | Whether the change breaks one transport (BFD count) |
| One transport | Can cut the router off from the Manager entirely | Whether control connections survive, with someone ready to act |
| Hub | Affects every branch that tunnels to it | Handle separately, one hub at a time, in its own window |
The record of the change should say what was learned. A short note covers it.
| Field | Entry |
|---|---|
| Change and reason | MPLS gateway 172.16.102.1 to 172.16.102.254 in the branch template, for the provider's gateway move |
| Scope | 40 branches, pushed in three groups: pilot, 5 sites, the rest |
| Baseline | Control connections 2, OMP prefixes 7, BFD sessions 4 on BR-02 |
| Success check | The same numbers after the push, with BFD on both transports |
| Undo | Push the old gateway value, decided at the first check that fails |
| Result | Pilot lost MPLS BFD, old value restored. Change on hold until the provider confirms the gateway move. |
Learn more: Configuration Deployment and Device AssociationsBackup, Change Windows and Lifecycle
Test yourself
You must change the default route in a template attached to 40 branches. What is the safest first step after previewing the change?
A read-only operator needs to watch alarms but should not be able to change a policy. Which control provides this?
After a push, a branch shows control connections down. The change touched its transport interface. What does this most likely mean?
After a pilot push, control connections and OMP prefixes match the baseline, but BFD sessions are 2 of 4. What do you do?
Why choose one pilot for each site pattern instead of the most convenient site?
Which parts of a change note let the next engineer decide when to stop and undo?