Migrate in phases, and plan the coexistence period
A new SD-WAN fabric rarely replaces a WAN overnight. Sites move in groups over weeks or months, and the sites that have not moved still depend on the old network. The hard part is therefore not the new design. It is the period in which both networks must work together, with users who notice neither.
Assess the current network, design the target and the meeting point, pilot one site, migrate in waves while both networks run, cut over the last sites, then retire the old network.
- Assessinventoryand needs
- Designtarget andmeeting point
- Pilotone site,proven
- Wavesold and newside by side
- Finishlast sitescut over
- Retireold networkremoved
Start from an inventory
Everything that the old network does quietly has to be found before the first cutover. A site that looks like a plain router and a circuit may also run a routing protocol with a neighbour, do address translation for a partner, mark traffic for voice, or hold a static route that nobody wrote down.
| Item | Why it matters | Where it hides |
|---|---|---|
| Circuits and bandwidth | Sets transport roles and the QoS shaping rate | Provider records, interface settings |
| Routing | Neighbours and protocols must be reproduced or replaced | Routing configuration and static routes |
| Address translation | Partners may depend on a translated address | NAT rules on the old router |
| QoS markings | Voice and business traffic must keep its treatment | Class maps and policy maps |
| Local services | DHCP relay, DNS and firewall rules may live on the router | Service and ACL configuration |
| Change window | Some sites cannot lose service at certain hours | Business owner of the site |
| Stage | Sites | Cutover nights | Work weeks of nights | Sites done after |
|---|---|---|---|---|
| Pilot | 2 | 1 | 0.2 | 2 |
| Wave 1 | 6 | 2 | 0.4 | 8 |
| Wave 2 | 10 | 4 | 0.8 | 18 |
| Wave 3 | 15 | 5 | 1.0 | 33 |
| Wave 4 | 15 | 5 | 1.0 | 48 |
Choose a coexistence pattern
There are two common ways to let old and new sites talk. In the first, an SD-WAN edge at a hub site connects to the old WAN and passes routes in both directions, so the hub is the gateway between the two worlds. In the second, the old circuit becomes one of the transports of the new edge, so the provider network carries both. Many migrations use both: the gateway at the hub and transport reuse at the branches.
With a gateway at the hub, an SD-WAN edge links the overlay to the old WAN and passes routes between them. With transport reuse, the old provider circuit becomes a transport of the new edge, so the overlay rides on it.
The hub gateway edge connects the overlay with the migrated branches on one side and the old WAN with the not yet migrated branches on the other.
- Migratedbranches onthe overlay
- Old WANprovider networkand legacy routers
- Data centershared servicesand applications
- Internetbreakout andcloud access
Exchange routes without creating loops
At the gateway, routes from the old WAN are advertised into the overlay and overlay routes are advertised back. Done at one point, this is simple. Done at two points without care, a prefix can leave the old WAN at the first gateway, enter the overlay, and return to the old WAN at the second as if it were a new route. That is a loop, or at best a long detour.
A route leaves the old WAN at the first gateway, the gateway adds a tag as it enters the overlay, the overlay carries the tag with the route, and the second gateway filters on the tag so the route does not re-enter the old WAN.
- Old WANroute leaves atgateway A
- Taggateway A addsthe tag
- Overlayroute travelswith its tag
- Filtergateway B blocksthe tagged route
| Control | What it does | Where it is applied |
|---|---|---|
| Tag or community on redistributed routes | Marks a route as coming from the other world | When the route is advertised across |
| Filter on the tag | Refuses to advertise a marked route back | At every gateway, in both directions |
| One gateway first | Removes the second point where loops could form | Early waves, before a second gateway is added |
| Prefix filters | Only the intended prefixes cross | On both sides of the gateway |
A worked case: reachable one way only
The branch BR-03 has just been cut over. Users there reach the data center, but cannot reach the not yet migrated branch BR-08. BR-08 stays on the old WAN, behind the hub gateway. The old WAN is advertised into the overlay, so the check starts at the migrated side, then follows the traffic across the gateway.
BR-03#show sdwan omp routes 203.0.113.0/24 PREFIX FROM PEER STATUS TLOC IP COLOR 203.0.113.0/24 10.255.0.11 C,I,R 10.255.1.1 mpls
LEGACY-HUB#show ip route 198.51.100.0 % Network not in table
BR-03 has a valid route to the old site through the hub gateway. The old WAN has no route back to BR-03. The prefix filter at the gateway does not list the new branch prefix.
- Forward pathBR-03 holds a chosen routePackets reach the hub gateway
- Old WANNo route to BR-03's prefixReplies are dropped
- Gateway filterLists earlier branches only198.51.100.0/24 is missing
- CauseWave added a branchFilter was not updated
| Filter line | BR-03 198.51.100.0/24 | BR-04 198.51.101.0/24 | BR-09 198.51.104.0/24 |
|---|---|---|---|
| permit 198.51.100.0/24 | Yes | No | No |
| permit 198.51.100.0/22 le 24 | Yes | Yes | No |
| permit 198.51.96.0/20 le 24 | Yes | Yes | Yes |
The repair is to add the new prefix, or a summary that covers the whole branch range, to the filter and to the migration checklist: every cutover includes a step that proves the old WAN learned the new prefix. The next test is a ping in both directions between a migrated site and an old one, because a one-way test would have passed here.
Cut over one site at a time, with a way back
A site cutover is short, planned and reversible. Stage the SD-WAN edge and verify its control connections before the window, so the window itself only moves the cables and the routing. Keep the old router powered and cabled until the rollback window closes.
| Step | Check | Rollback trigger |
|---|---|---|
| Stage the edge | Control connections up, tunnels up, on the bench or in parallel | Do not start the window if any check fails |
| Move the site | LAN gateway and routing now on the new edge | No LAN reachability after the agreed time |
| Verify both ways | Ping and application tests to a migrated site and to an old site | Either direction fails |
| Watch the baseline | Tunnel count, routes and voice quality as expected | Voice or a key application degraded |
| Close the window | Rollback window passes; old device removed later | Not applicable |
Learn more: Hub-and-Spoke vs MeshOMP Route AttributesFault Injection and Cutover Validation
Test yourself
A branch is cut over. It reaches the data center but not a branch that is still on the old WAN. The overlay route to the old branch is chosen and installed. Where do you look next?
Two gateways pass routes in both directions between the overlay and the old WAN, and some prefixes now take long detours. What is the likely cause and the control?
When can the old router at a migrated site be removed?
Why start with one gateway at the hub rather than two?
The gateway filter reads permit 198.51.100.0/22 le 24. Which of these branch prefixes does it pass?
A plan has 30 sites left and the team can cut over 3 sites a night. How many cutover nights are needed, and how many work weeks of 5 nights is that?
A tag is added to routes as they cross from the old WAN into the overlay, but loops still form at the second gateway. What is missing?